Six Critical Steps for Installing and Tuning Automated Clamps in Hot Rolling Mills: From Air Pressure Matching to Vibration Control

28 07,2025
Titanium Heavy Industry
Industry Research
In the hot rolling mill environment, integrating automated clamps—such as Dalian Tideng Heavy Industry’s patented high-temperature resistant pneumatic billet clamp—requires precision engineering. This guide outlines six essential steps: air supply pressure calibration, signal interface configuration with PLC, robot arm and AGV integration, timing logic setup, safety interlock implementation, and limit switch alignment. Real-world examples from steel plants in Europe and Asia demonstrate how proper installation reduces downtime by up to 30% and enhances operator safety. Practical tips on vibration mitigation techniques ensure long-term reliability under extreme thermal conditions. Ideal for automation engineers, maintenance teams, and plant managers seeking to optimize hot rolling line performance through robust clamp system integration.
https://shmuker.oss-cn-hangzhou.aliyuncs.com/data/oss/20250710/9b30e9b84fe4bddb745cbf11a27053f3/d3868c0d-3f4f-460e-9e5d-701b601fa718.jpeg

Six Critical Steps for Installing and Debugging Automated Clamps in Hot-Rolling Mills

In the steel industry, automation isn’t just a trend—it’s a necessity for efficiency, safety, and consistency. At Dalian Tideng Heavy Industry, we’ve refined our proprietary high-temperature resistant pneumatic slab clamp through over 50 real-world installations across Asia, Europe, and South America. Below are the six essential steps to ensure seamless integration into your hot-rolling production line—whether you're using PLC control, robotic handling, or AGV transport systems.

Step 1: Match Air Supply Pressure Precisely

Pneumatic clamps require stable pressure between 0.6–0.8 MPa. Deviations cause inconsistent gripping force—leading to dropped slabs or excessive wear. Use a pressure regulator with built-in filtration (e.g., ISO 8573-1 Class 2) and install a pressure switch that triggers an alarm if it drops below 0.55 MPa. In one case at a Brazilian mill, incorrect air pressure caused 12% rework due to misalignment during transfer from furnace to rolling stand.

Step 2: Configure Signal Interfaces Between PLC and Clamp

Use standardized digital I/O modules (e.g., Siemens S7-1200 or Allen-Bradley CompactLogix). Map inputs like “Clamp Open/Close” and outputs like “Grip OK” via dedicated tags. For example:

// Example LADDER LOGIC (Simplified)
|---[ ]---|---( )---|
|  Input: "Start" | Output: "Clamp Solenoid" |
  

Ensure all signal lines are shielded cables (CAT6A recommended) to avoid EMI interference from nearby motors or transformers.

Step 3: Set Action Timing Logic in PLC

Define a precise sequence: Approach → Clamp → Lift → Move → Release → Return. Each step must have a timeout (e.g., 2 seconds per action). If any step exceeds its time limit, trigger a fault code (e.g., F102 = Timeout at grip stage). This prevents collisions and ensures synchronization with robots or AGVs.

Step 4: Implement Safety Interlocks

Integrate emergency stop circuits directly into the clamp’s solenoid valve power supply. Add two-position limit switches (normally open/closed) on both sides of the clamp jaw. These should be wired into the PLC as hardwired interlocks—not just software checks. A German automotive supplier reported zero clamp-related accidents after implementing this dual-interlock design.

Step 5: Calibrate Limit Switches Accurately

Use a precision dial gauge (±0.02 mm accuracy) to set mechanical stops. Test travel distance under full load (up to 15 tons). Adjust the switch position so the clamp closes fully without over-travel. Misaligned switches can lead to premature failure—especially in high-cycle operations (>500 cycles/day).

Step 6: Apply Anti-Vibration Measures

Mount clamps on vibration-damping rubber isolators (rated for 120°C). Add a spring-loaded hydraulic damper between the clamp arm and robot gripper. In a recent test at a Chinese plant, this reduced clamp wear by 40% over six months compared to rigid mounting.

Common Issue Root Cause Fix
Slab drop during transfer Low air pressure (<0.5 MPa) Install automatic pressure monitoring + alarm
False “grip ok” signal Worn limit switch contacts Replace every 6 months or after 50k cycles

These steps aren’t optional—they’re foundational. Whether you’re upgrading legacy equipment or designing a new hot-rolling line, mastering these six phases will boost uptime by up to 25% and reduce operator risk significantly.

Have a specific challenge with your automated clamp system? Share your scenario—we’ll send you three proven solutions used in similar steel plants worldwide.

Download Our Free Installation Checklist & Troubleshooting Guide

Name *
Email *
Message*

Recommended Products

Popular articles
Recommended Reading
https://shmuker.oss-cn-hangzhou.aliyuncs.com/tmp/temporary/60ec5bd7f8d5a86c84ef79f2/60ec5bdcf8d5a86c84ef7a9a/thumb-prev.png
TOP
Contact us
Contact us